How to construct a Road


                  HOW    TO     CONSTRUCT     A     ROAD
There    are     four      stages      to     consider     when            trying     to       construct     a   road.  The     stages    are    as     follows: (1) General      (2)Demolition,site clearance    and      earthworks  ( 3)Construction  of  culverts   and   Drains   and (4)   Road  pavement   /surfacing.
(1)General
      The   client   Representative(consultant)  will   be   provided   with   a   well   furnish  and  maintain   office    accommodation  as    specified    according   to   schedule  No.  IV.
       The    consultant  is     also     provided   with   equipment,labour   and   assistance   as   may
       be   required  in   accordance    with   schedule   No IV.
        Provide   and    maintain     living       accommodation  for    the   client  representative and  resident  engineer  to  standards     specified   in     scheduled   No.   IV.
         Allow     for    the    provision    of    the   following  : erection  of   road  signs,road  markings,compensation&acquisition  ,progress   photographs,stationery  and   equipment,furniture  for   consultant   living   room,payment  of  wages   to   casual   staff  of
the   client    representative,purchase  -maintennance  and   running  cost     of    the    official   transport     vehicle     for   the    consultant,removal/relocation   of    existing   installation   for
electricity,telephone  and    water.Allow    for   planting    ,nursing  and   growth   of  beautification   of     trees   at   road   side.Allow    for      laboratory   equipment,provision   of
personal  computer,printers,video   camera,software  and   accessories. Allow    for   deep   soil
investigation.
(2)Demolition,site  clearance   and   earthwork
      Clear    site   15meter     wide   on     each   side   of    centerline   of    road   to    remove    shrub   grass   and     trees    including    topsoil   to   a    depth    of    150mm. Excavate   any    material  except   rock   and   side  drains,haul   excavated    materials    any    distance,deposit,spread   in   150mm   layers   and   compact    to   100%B.S.  Compaction   as   filing   for     embarkments    and    trim  slopes    to   requied    cross-section.Excavate   from    approved    borrow   pits,  haul   excavated    material     any   distance,  deposit   spread   in  150mm   layers  and    compact   to    100%B.S  Compaction   as   filling    for  embarkments   and    margins      formation    and   trim   slopes    to   reqDub  in   grass   to     slope    of    embarkment    and    verges   as   specified   and   directed   .Excavate     unsuitable      material      as   directed  by   the   engineer  and   dispose   to    spoil.provide    approved    fill   materials   in   marshy  and  swanpy   areas   as     specified.Provide    and     place   200mm   thick   rip-rap   protection    to    embarkment    slopes.
(3)culverts    and   Drains
Demolish    existing    bungalow   building     where   required   and    dispose   of   all    materials   as    directed    by   the   engineers.Excavate    for    all    culverts   concrete     side    drains   and   turnout   to     any   depth  in    any   material    except   rock    including    backfilling    to    100%B.S.  Compaction     and     dispose    of    surplus        materials     as   directed   by   the    engineer.Provide   for     and   construct   900mm    diameter    concrete    pipe    culvert,complete   with concrete     blinding,bedding,haunching   and    surround.Including    shuttering,headwalls,wingwalls  and    aprons,   all    complete.ageProvide    for    ,   and    construct       grade   20    side   drains   cross  section  0.7mx0.9m  as    specified   in    the    drawing.Provide    and   place    reinforced    precast    concrete    grade   30    drain   slab    covers     as     directed   by  the    engineer(see    drawings).Provide   and   fix   high   yield    reinforcement    in  precast     slab.
(4)Pavement  and   surfacing
         Provide,spread,shape   and    compact    to    150mm     finished    thickness   lateritic   materials(include   haulage)as    specified  in   base.Provide   spread   slope    compact     to   100%   west   Africa    standard    compaction     approved  laterite    material   in  layers   no   exceeding  150mm  on   the   shoulder(haul  Provide      and   lay    prime    coat    using      MCO   or   MCI        cutback   
Bitumen  at    1  litre   per   sq    including     blinding   with     sand      and     quarry   fine.Provide   ,lay   and    compact    asphaltic   concrete     binder     course   to   a    compacted     thickness   of   50mm    carriageway   as    specified.
Provide     ,lay  and   compact    asphaltic     concrete    wearing        course    to   a     compacted       thickness    of   40mm   ageway    as    specified.