ROAD PLANNING AND
RECONNAISSANCE
1 Route Planning
Planning with
respect to road construction takes into account present and future uses of
the transportation system to assure maximum service with a minimum of
financial and environmental cost. The main objective of this initial phase of
road development is to establish specific goals and prescriptions for road
network development along with the more general location needs. These goals
must result from a coordinated effort between the road engineer and the land
manager, forester, geologist, soil scientist, hydrologist, biologist and
others who would have knowledge or recommendations regarding alternatives or
solutions to specific problems. The pattern of the road network will govern
the total area disturbed by road construction.
The road pattern
which will give the least density of roads per unit area while maintaining
minimum hauling distance is the ideal to be sought. Keeping the density of
roads to an economical minimum has initial cost advantages and future
advantages in road maintenance costs and the acreage of land taken out of
production.
Sediment control
design criteria may be the same as, or parallel to, other design criteria
which will result in an efficient, economical road system. Examples of overlap
or parallel criteria are:
1.
Relating road
location and design to total forest resource, including short and long term
harvest patterns, reforestation, fire prevention, fish and wildlife
propagation, rural homestead development, and rangeland management.
2.
Relating road
location and design to current and future timber harvesting methods.
3.
Preparing road
plans and specifications to the level of detail appropriate and necessary to
convey to the road builder, whether timber purchaser or independent
contractor, the scope of the project, and thus allow for proper preparation
of construction plans and procedures, time schedules, and cost estimates.
4.
Writing
instructions and completing companion design decisions so as to minimize the
opportunity for "changed conditions" during construction with
consequent costs in money and time.
5.
Analyzing
specific road elements for "up-front" cost versus annual
maintenance cost (for instance, culvert and embankment repair versus bridge
installation, ditch pavement or lining versus ditches in natural soil, paved
or lined culverts versus unlined culverts, sediment trapping devices
("trash racks", catch basins, or sumps) versus culvert cleaning
costs, retaining walls or endhauling sidecast versus placing and maintaining
large embankments and fill slopes, roadway ballast or surfacing versus
maintenance of dirt surfaces, and balanced earthwork quantities versus waste
and borrow).
The route
planning phase is the time to evaluate environmental and economic tradeoffs
and should set the stage for the remainder of the road development process.
Although inclusion of design criteria for sediment control may increase
initial capital outlay, it does not necessarily increase total annual cost
over the life of the road which might come from reductions in annual
maintenance, reconstruction, and repair costs (see Section 2.2). If an
objective analysis by qualified individuals indicates serious erosional
problems, then reduction of erosional impacts should be a primary concern. In
some areas, this may dictate the location of control points or may in fact
eliminate certain areas from consideration for road construction as a result
of unfavorable social or environmental costs associated with developing the
area for economic purposes.
2.1.1
Design Criteria
Design criteria
consist of a detailed list of considerations to be used in negotiating a set
of road standards. These include resource management objectives,
environmental constraints, safety, physical environmental factors (such as
topography, climate, and soils), traffic requirements, and traffic service
levels. Objectives should be established for each road and may be expressed
in terms of the area and resources to be served, environmental concerns to be
addressed, amount and types of traffic to be expected, life of the facility
and functional classification. Additional objectives may also be defined
concerning specific needs or problems identified in the planning stage.
1.
Resource
management objectives: Why is the road being built; what is the purpose of the
road (i.e., timber harvesting, access to grazing lands, access to
communities, etc.)?
2.
Physical and
environmental factors: What are the topographic, climatic, soil and
vegetation characteristics of the area?
3.
Environmental
constraints: Are there environmental constraints; are there social-political
constraints? Examples of the former include erosiveness of soils, difficult
geologic conditions, high rainfall intensities. Examples of the latter
include land ownership boundaries, state of the local economy, and public
opinion about a given project.
4.
Traffic
requirements: Average daily traffic (ADT) should be estimated for different
user groups. For example, a road can have mixed traffic--log or cattle trucks
and community traffic. An estimate of traffic requirements in relation to use
as well as changes over time should be evaluated.
5.
Traffic service
level: This defines the type of traffic that will make use of the road
network and its characteristics. Table 3 lists descriptions of four different
levels of traffic service for forest roads. Each level describes the traffic
characteristics which are significant in the selection of design criteria and
describe the operating conditions for the road. Each level also reflects a
number of factors, such as speed,travel time,traffic interruptions, freedom
to maneuver, safety, driver comfort, convenience, and operating cost. Traffic
density is a factor only if heavy non-logging traffic is expected. These
factors, in turn, affect: (1) number of lanes, (2) turnout spacing, (3) lane
widths, (4) type of driving surface, (5) sight distances, (6) design speed,
(7) clearance; (8) horizontal and vertical alignment, (9) curve widening,
(10) turn-arounds.
6.
Vehicle
characteristics: The resource management objectives, together with traffic
requirements and traffic service level criteria selected above, will define
the types of vehicles that are to use the proposed road. Specific vehicle
characteristics need to be defined since they will determine the "design
standards" to be adopted when proceeding to the road design phase. The
land manager has to distinguish between the "design vehicle" and
the "critical vehicle". The design vehicle is a vehicle which
ordinarily uses the road, such as dual axle flatbed trucks in the case of
ranching or farming operations, or dump trucks in the case of a mining
operation. The critical vehicle represents a vehicle which is necessary for
the contemplated operation (for instance, a livestock truck in the case of
transporting range livestock) but uses the road infrequently. Here, the
design should allow for the critical vehicle to pass the road with assist
vehicles, if necessary, but without major delays or road reconstruction.
7.
Safety: Traffic
safety is an important requirement especially where multiple user types will
be utilizing the same road. Safety requirements such as stopping distance,
sight distance, and allowable design speed can determine the selected road
standards in combination with the other design criteria.
8.
Road uses: The
users of the contemplated road should be defined by categories. For example,
timber harvest activities will include all users related to the planned
timber harvest, such as silviculturists, foresters, engineers, surveyors,
blasting crews, and construction and maintenance crews, as well as the
logging crews. Administrative users may include watershed management
specialists, wildlife or fisheries biologists, or ecologists, as well as
foresters. Agricultural users would include stock herders and rangeland
management specialists and will have a different set of objectives than
timber objectives. An estimate of road use for each category is then made
(e.g., numbers of vehicles per day). For each category, the resource
management objective over several planning horizons should be indicated. For
instance, a road is to be built first for (1) the harvest of timber from a
tract of land, then (2) access for the local population for firewood cutting
or grazing, and finally (3) access for administration of watershed
rehabilitation activities. The planner should determine if the road user
characteristics will change over the life of the road.
9.
Economics: The
various road alternatives would undergo rigorous economic evaluations.
As part of this
process a"roads objectives documentation" plan should be carried
out. This process consists of putting the road management objectives and
design criteria in an organized form. An example of such a form is given in
Table 4.
Table 3. Traffic service levels definitions used to
identify design parameters (from U.S. Forest Service, Transportation
Eng. Handbook).
|
A
|
B
|
C
|
D
|
FLOW
|
Free flowing
with adequate passing facilities.
|
Congested
during heavy traffic such as during peak logging or recreation activities.
|
Interrupted by
limited passing facilities, or slowed by the road condition.
|
Flow is slow
or may be blocked by an activity. Two way traffic is difficult and may
require backing to pass.
|
VOLUMES
|
Uncontrolled;
will accommodate the expected traffic volumes.
|
Occasionally
controlled during heavy use periods.
|
Erratic;
frequently controlled
as the capacity is reached.
|
Intermittent
and usually controlled. Volume is limited to that associated with the
single purpose.
|
VEHICLE
TYPES
|
Mixed;
includes the critical vehicle and all vehicles normally found on public
roads.
|
Mixed;
includes the critical vehicle and all vehicles normally found on public
roads.
|
Controlled
mix; accommodates all vehicle types including the critical vehicle. Some
use may be controlled to minimize conflicts between vehicle types.
|
Single use;
not designed for mixed traffic. Some vehicles may not be able to negotiate.
Concurrent use between commercial and other traffic is restricted.
|
CRITICAL
VEHICLE
|
Clearances are
adequate to allow free travel. Overload permits are required.
|
Traffic
controls needed where clearances are marginal. Overload permits are
required.
|
Special provisions
may be needed. Some vehicles will have difficulty negotiating some
segments.
|
Some vehicles
may not be able to negotiate. Loads may have to be offloaded and walked in.
|
SAFETY
|
Safety
features are a part of the design.
|
High priority
in design. Some protection is accomplished by traffic management.
|
Most
protection is provided by traffic management
|
The need for
protection is minimized In by low speeds and strict traffic controls.
|
TRAFFIC
MANAGEMENT
|
Normally
limited to regulatory, warning, and guide signs and permits.
|
Employed to
reduce traffic volume and conflicts.
|
Traffic
controls are frequently needed during periods of high use by the dominant
resource activity.
|
Used to
discourage or prohibit traffic other than that associated with the single
purpose.
|
USER
COSTS
|
Minimize;
transportation efficiency is important.
|
Generally
higher than "A" because of slower speeds and increased delays.
|
Not important;
efficiency of travel may be traded for lower construction costs.
|
Not
considered.
|
ALIGNMENT
|
Design speeds
is the predominant factor within feasible topographic limitations.
|
Influenced
more strongly by topography than by speed and efficiency.
|
Generally dictated by topographic features and environmental factors.
Design speeds are generally low.
|
Dictated by
topography, environmental factors, and the design and critical vehicle
limitations. Speed is not important.
|
ROAD
SURFACE
|
Stable and
smooth with little or no dust, considering the normal season of use.
|
Stable for the
predominant traffic for the normal use season. Periodic dust control for
heavy use or environmental reasons. Smoothness is commensurate with the
design speed.
|
May not be
stable under all traffic or weather conditions during the normal use
season.. Surface rutting, roughness, and dust may be present, but
controlled for environmental or investment protection.
|
Rough and
irregular. Travel with low clearance vehicles is difficult. Stable during
dry conditions. Rutting and dusting controlled only for soil and water
protection.
|
Design Elements
A road design
standard consists of such elements as the definitive lengths, widths, and
depths of individual segments (e.g., 4.3 meter traveled way, 0.6 meter
shoulders, 3/4:1 cutslopes, 1 meter curve widening, 15 cm of crushed
aggregate surfacing). Figure 6 illustrates the road structural terms that
will be used throughout the rest of this handbook. Selection of the appropriate
road design standard is critical to the overall efficiency of the road
network to be installed, and certain elements will have a more rigid standard
than others depending on the location of the road or road segment. The entire
range of values for each standard must be evaluated and selected according to
their appropriateness for a given segment. Then, the various design elements
must undergo testing to ensure that the final design meets the previously
agreed upon management objectives. For instance, on steeper grades vertical
alignment has a greater effect on travel speed than horizontal alignment.
Therefore, surfacing and horizontal alignment should not be improved to
increase speed where the road gradient is the controlling element.
Figure 6. Road structural terms.
Table 4. Example of a roads objective documentation
form (from U.S. Forest Servise, Transportation Eng. Handbook).
Number of Lanes and Lane Width
The majority of
forest development road systems in the world are single-lane roads with
turnouts. It is anticipated that most roads to be constructed or
reconstructed will also be single-lane with turnouts because of the
continuing need for low volume, low speed roads and their desirability from
economic and environmental impact standpoints. In choosing whether to build a
single- or double-lane road, use the best available data on expected traffic
volumes, accident records, vehicle sizes, and season and time-of-day of use.
Historically, the United States Forest Service has used traffic volumes of
approximately 100 vehicles per day to trigger an evaluation for increasing
road width from one to two lanes. Considering a day to consist of 10 daylight
hours, traffic volumes greater than 250 vehicles per day ordinarily require a
double-lane road for safe and efficient operation. Intermediate traffic
volumes (between 100 and 250 vehicles per day) generally require decisions
based on additional criteria to those listed above: (1) social/political
concerns, (2) relationships to public road systems, (3) season of use, (4)
availability of funding, and (5) traffic management.
Many of the
elements used in such an evaluation, although subjective, can be estimated using
traffic information or data generated from existing roads in the area. For
instance, if heavy public use of the road is anticipated, a traffic count on
a comparably situated existing road will serve as a guide to the number of
vehicles per hour of non-Jogging traffic. Some elements can be
evaluated in terms of relative probabilities and consequences and can be
identified as having a low, moderate, or high probability of occurrence and
having minor, moderate, or severe consequences. The more criteria showing
higher probabilities and more severe consequences, the stronger the need for
a double-lane road.
2.1.2.2
Road width
The primary
consideration for determining the basic width of the road bed is the types of
vehicles expected to be utilizing the road. Secondary considerations are the
general condition of the traveled way, design speed, and the presence or
absence of shoulders and ditches. Tables 5 and 6 list recommended widths for
single- and double-lane roads, respectively.
Table 5. Traveled way widths for single-lave roads.
Type
and Size of Vehicle
|
Design
Speed (Km/Hr)
|
30
|
40
|
50
|
|
Minimum Traveled Way Width (m)
|
Recreational,
administrative and service vehicle, 2.0 to 2.4 m wide
|
3.0
|
3.0
|
3.6
|
Commercial
hauling and commercial passenger vehicles, including buses 2.4 m wide or
greater
|
|
|
|
1. Road with
ditch, or without ditch where cross slope is 25% or less
|
3.6
|
3.6
|
4.2
|
2. Roads
without ditch where ground cross slope is greater than 25%. The steepness
of roadway backslope should be considered to provide adequate clearance.
|
3.6
|
3.6
|
4.2
|
The presence of
a ditch permits a narrower traveled way width since the ditch provides the
necessary clearance on one side. Except for additional widths required for
curve widening, limit traveled way widths in excess of 4.4 m (14 ft) to roads
needed to accommodate off -highway haul and other unusual design vehicles.
Double-lane roads designed for off-highway haul (all surface types) should
conform to the following standards:
Table 6. Lane widths for double-lane roads.
Size
and Type of Vehicle
|
Type
of Road
|
Type
of Surface
|
Type
Design Speed (Km/Hr)
|
15
|
30
|
45
|
60
|
80
|
Recreational,
adm. and service:
|
|
|
Minimum Lane Width (m)
|
1. up to 2.0 m
wide
|
Recreation
or administrative
|
All
surface types
|
2.7
|
2.7
|
3.0
|
3.3
|
3.0
|
2. 2.0 to 2.4
m wide
|
3.0
|
3.0
|
3.3
|
3.3
|
3.3
|
Commercial
hauling and comm. passenger native vehicles incl. buses 2.4 m wide or
greater
|
Roads
open to truck traffic or mixed traffic
|
Gravel
or native
|
-
|
3.3
|
3.6
|
3.6
|
-
|
Bituminous
|
-
|
3.3
|
3.3
|
3.3
|
3.6
|
Gravel or
native surface roads should not have design speeds greater than 60 km/hr
Additional width is required for lower quality surfaces, because of the
off-tracking corrections needed compared to a higher quality surface.
|
Vehicles wider
than the design vehicle (a "critical vehicle") may make occasional
use of the road. Check traveled way and shoulder widths to ensure that these
vehicles can safely traverse the road. Critical vehicles should never attempt
to traverse the road at or even approaching the speeds of the design vehicle.
Shoulders may be
necessary to provide parking areas, space for installations such as drainage
structures, guardrails, signs, and roadside utilities, increase in total
roadway width to match the clear width of an opening for a structure such as
a bridge or tunnel, a recovery zone for vehicles straying from the traveled
way, additional width to accommodate a "critical vehicle", lateral
support for outside edge of asphalt or concrete pavements (0.3 m is sufficient
for this purpose). The space required for these features will depend on the
design criteria of the road and/or the design of specific structures to be
incorporated as part of the roadway.
Minimum
Width of Traveled Way for Design Speed
|
Bunk
Width
|
30
km/hr(20 mph)
|
50
km/hr (30 mph)
|
60
km/hr (40 mph)
|
3.0
m (10 ft)
|
6.7
m (22 ft)
|
7.3
m (24 ft)
|
7.9
m (26 ft)
|
3.7
m (12 ft)
|
7.9
m (26 ft)
|
8.5
m (28 ft)
|
8.5
m (28 ft)
|
2.1.2.3.
Turnouts
Turnout spacing,
location, and dimensions provide user convenience and safety and allow
vehicles to maintain a reasonable speed. Spacing can be computed using the
following formula and the curves from Figure 7 and Table 7:
T =
1.609*(DS)/36
Where:
T = Increase in
travel time for the interrupted vehicle (percent)
D = Delay Lime per kilometer for the interrupted vehicle (seconds)
S = Design speed (kilometers per hour).
Solve the
equation for T and then use the graph in Figure 7 to determine the turnout
spacing required to accommodate the number of vehicles passing over the road
per hour (VPH).
Figure 7. Turnout spacing in relation to traffic volume
and travel delay time.
Table 7. Recommended turnout spacing--all traffic
service levels
Traffic
Service
|
Turnout
Spacing
|
Operational
Constraints
|
A
|
Make turnouts
intervisible unless
excessive costs or environmental constraints preclude construction
Closer spacing may contribute
to efficiency and convenience.
Maximum spacing is 300 m.
|
Traffic: Mixed
Capacity: Up to 25 vehicles per hour
Design Speed: Up to 60 km/hr
Delays: 12 sec./km or less
|
B
|
Intervisible
turnouts are highly
desirable but may be precluded
by excessive costs or environmental constraints. Maximum spacings 300 m.
|
Traffic: Mixed
Capacity: Up to 25 vehicles per hour Design Speed: Up to 40 km/hr
Delays: 20 km/hr or less
Use signs to warn non commercial users of traffic to be expected. Road
segments without intervisible turn-outs should be signaled.
|
C
|
Maximum
spacing is 300 m.
When the environmental impact is low and the investment is economically
justifiable, additional turnouts may be
constructed.
|
Traffic: Small
amount of mixed
Capacity: Up to 20 vehicles per hour Design Speed: Up to 30 km/hr
Delays: Up to 40 sec./km
Roads should be managed to mini mize conflicts between commercial and
non-commercial users.
|
D
|
Generally,
only naturally occurring
turnouts, such as on ridges or
other available areas
on flat terrain, are used.
|
Traffic: Not
intended for mixed
Capacity: Generally 10 VPH or less Design Speed: 25 km/hr or less
Delays: At least 45 sec./km expected. Road should be managed to restrict
concurrent use by commercial and non-commercial users.
|
Figure 8
illustrates a typical turnout in detail. Turnouts should be located on the
outside of cuts, the low side of fills, or at the runout point between
through cuts and fills, and preferably on the side of the unloaded vehicle.
Table 8 gives recommended turnout widths and lengths for various traffic
service levels. The maximum transition length should be limited to 22.5 m for
all service levels.
Figure 8. Typical turnout dimensions.
Table 8. Turnout widths and lengths.
Traffic
Service Levels
|
Turnout
Width
|
Turnout
Length & Transition Length
|
A
|
3.0
m
|
Design vehicle
length or 22.5 m minimum, whichever is largest. Minimum 15 m transition at
each end.
|
B
|
3.0
m
|
Design vehicle
length.
Minimum 15 m transition at each end.
|
D
|
Make the
minimum total width of the traveled way and turnout the width of two design
vehicles plus 1.2 m
|
Empty truck
length (trailer loaded on truck)
Minimum 7.5 m transitions at each end.
|
2.1.2.4.
Turn-arounds
Turn-around
design should consider both critical and design vehicles and should be
provided at or near the end of single-lane roads, and at management closure
points, such as gates or barricades. If intermediate turn-arounds are
necessary, signing should be considered if they create a hazard to other
users. The turn-around should be designed to allow the design vehicle to turn
with reasonably safe maneuvering.
2.1.2.5.
Curve Widening
Widening may be
required on some curves to allow for off-tracking of tractor-trailer vehicles
and for some light vehicle-trailer combinations. Widening of the traveled way
on curves to accommodate the design vehicle is considered a part of the
traveled way. Generally, the need for curve widening increases as curve
radius decreases with shorter curves requiring less curve widening than
longer curves. Criteria for establishing the need for curve widening given
traffic service levels are given in Table 9.
Table 9. Curve widening criteria
Traffic
Service Level
|
Curve
Widening
|
A
|
Design curve
widening to accommodate the design vehicle (normally low-boy) at the design
speed for each curve. Curve widening for critical vehicles to be provided
by the use of other road elements, if planned, such as turnouts and
shoulders. Provide widening if needed width is not available. Critical
vehicle should be accommodated in its normal traveling configuration. Curve
widening to be provided in each lane of double-lane roads.
|
B
|
Same as A.
|
C
|
Same as A,
except the critical vehicle configuration may need alteration.
|
D
|
Curve widening
to be provided only for the design vehicle. Loads carried by the critical
vehicle should be off-loaded and walked to the project or transferred to
vehicles capable of traversing the road. Temporary widening to permit the
passage of larger vehicles may be accomplished by methods such as
temporarily filling of the ditch at narrow sections.
|
.
Clearance
The desired minimum
horizontal clearance is 1.2 m (4 ft) the minimum vertical clearance is 4.3 m
(14 ft). At higher speeds consideration should be given to increasing the
clearances..
Speed and Sight Distance
Design speed is
the maximum safe speed that the design vehicle can maintain over a specified
segment of road when conditions are so favorable that the design features of
the road govern rather than the vehicle operational limitations. The selected
design speed establishes the minimum sight distance for stopping, passing,
minimum radius of curvature, gradient, and type of running surface.
Alternative combinations of horizontal and vertical alignment should be
evaluated to obtain the greatest sight distance within the economic and
environmental constraints. Suggested horizontal curve radius for a packed
gravel or dirt road with no sight obstruction is 33 and 62 m (108 and 203 ft)
for design speeds of 24 and 32 km/hr (15 and 20 mph), respectively. For
curves with a sight obstruction 3 m (10 ft) from the travel way, horizontal
curve radii are 91 and 182 m (300 and 600 ft), respectively. Suggested
vertical curve length is 61 m (200 ft). Recommended stopping distances for
single-lane roads with a maximum pitch of 2 percent (horizontal and vertical
control) and traffic service level C or D are:
km/hr (MPH)
|
Stopping
Distance, meters (feet)
|
16
(10)
|
21.3
(70)
|
24
(15)
|
36.5
(120)
|
32
(20)
|
54.9
(180)
|
48
(30)
|
94.5
(310)
|
For a more
comprehensive discussion on stopping sight distance and passing sight
distance, the reader is referred to the following sources: Route Location and
Design, by Thomas F. Hickerson; USDA, Forest Service Handbook # 7709.11,
"Transportation Engineering Handbook"; Bureau of Land Management,
Oregon State Office, "Forest Engineering Handbook"; or
"Geometric Design Standards for Low Volume Roads", Transportation
Research Board.
2.1.2.8.
Horizontal and Vertical Alignment
For low volume
roads with design speeds of 24 kph (15 mph) or less, a horizontal alignment
that approximates the geometric requirements of circular curves and tangents
may be used. Alignment should be checked so that other design elements, such
as curve widening and stopping sight distance can be considered. A minimum
centerline radius of curvature for roads should be 15 meters (50 ft) except
for some recreation and administrative roads. Superelevation should not be
used for design speeds less than 32 kph (20 mph). If snow and ice are
factors, the superelevation rate should not exceed 6 percent and should be
further reduced on grades to accommodate slow truck traffic. Transition
segments into and out of superelevated sections should be provided to avoid
abrupt changes in the roadway template.
Vertical
alignment, or grade; is of critical concern because of its potential for
environmental damage and becomes increasingly important for grades exceeding
10 percent. Erosion potential increases as a function of the square of the
slope and the cube of water velocity. The Most desirable combination of grade
and other design elements should be determined early in the road location
phase with additional caution exercised when grades exceed 8 percent.
Vertical alignment normally governs the speed of light vehicles for grades
exceeding 15 percent favorable and 11 percent adverse and of loaded trucks
for grades exceeding 8 percent favorable and 3 percent adverse. The ability
of a vehicle to traverse a particular grade is dependent on vehicle weight
and horsepower and on the traction coefficient of the driving surface.
Travel time and
cost are affected by horizontal alignment, such as curve radius and road
width. Figure 9 shows the relationship between average truck speed and curve
radius for several road widths. For example, there is a 15 percent difference
in average truck speed on a 30.5 m (100 ft) radius curve for a 3.7 m wide
road when compared to a 4.3 m wide road. Horizontal alignment has been
classified on the basis of curve radius and number of curves. The U. S.
Forest Service, for example, uses the following classification system:
[Average
radius (m)] / [# of curves / km]
|
Poor
|
=
|
<
4
|
Good
|
=
|
10
- 20
|
Fair
|
=
|
4
- 10
|
Excellent
|
=
|
>
20
|
The effect of
grade on truck speed (loaded and unloaded) is shown in Figure 10. The speed
of a loaded truck is most sensitive to grade changes from 0 to 7 percent in
the direction of haul. For grades steeper than 7 percent other considerations
are more important than impact on speed.
Figure 9. Relationship between curve radius and truck speed
when speed is not controlled by grade.
Figure 10. Relationship between grade and truck speed on
gravel roads.
.
Travel Time
It is important
to emphasize that travel time is influenced by grade, nature of road surface,
alignment, roadway width, sight distance, climate, rated vehicle performance,
and psychological factors (such as fatigue, degree of caution exercised by
driver, etc.). Table 10 shows travel time for loaded and empty trucks over
paved, graveled, and dirt surfaces as influenced by vertical and horizontal
alignment. The information from Table 10 is helpful in the planning stage to
assess the effects of vertical and/or horizontal alignment, road surface and
width on travel time and costs. The planned road should be divided up into
segments of similar vertical and/or horizontal alignment sections. Average
times can be calculated for each segment and/or road class and summed.
Table 10a. Relationship between round trip travel time
per kilometer and surface type as influenced by vertical and horizontal
alignment; adverse grade in direction of haul (U.S.
Forest service, 1965).
Class
of Road [1]
|
Percent
Grade in Direction of Load (Adverse)
|
+10
|
+9
|
+8
|
+7
|
+6
|
+5
|
+4
|
|
+2
|
0
|
min
/ km
|
1
|
Lane and
one-half with turnouts (car lane and truck lane with 4-ft. ditch)[2]
|
|
|
|
|
|
|
|
|
|
|
|
A
|
Alignment
excellent:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Paved
|
7.93
|
7.28
|
6.59
|
5.93
|
5.28
|
4.59
|
3.95
|
-
|
2.95
|
2.42
|
|
|
2. Gravel
|
8.21
|
7.56
|
6.87
|
6.21
|
5.53
|
4.84
|
4.23
|
-
|
3.20
|
2.42
|
|
B
|
Alignment
good:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Paved
|
7.93
|
7.28
|
6.59
|
5.93
|
5.32
|
4.78
|
4.25
|
-
|
3.25
|
3.01
|
|
|
2. Gravel
|
8.21
|
7.56
|
6.87
|
6.21
|
5.57
|
5.03
|
4.53
|
-
|
3.50
|
3.01
|
|
C
|
Alignment
fair:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Paved
|
7.93
|
7.28
|
6.62
|
6.12
|
5.62
|
5.09
|
4.56
|
-
|
3.61
|
3.61
|
|
|
2. Gravel
|
8.21
|
7.56
|
6.90
|
6.40
|
5.87
|
5.34
|
4.84
|
-
|
3.81
|
3.61
|
2
|
Single lane
with turnouts (truck lane with 3-ft. ditch)[2]:
|
|
|
|
|
|
|
|
|
|
|
|
A
|
Alignment
excellent:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Paved
|
7.93
|
7.28
|
6.59
|
5.93
|
5.28
|
4.59
|
4.02
|
-
|
3.02
|
2.58
|
|
|
2. Gravel
|
8.21
|
7.56
|
6.87
|
6.21
|
5.53
|
4.84
|
4.30
|
-
|
3.27
|
2.58
|
|
B
|
Alignment
good:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Paved
|
7.93
|
7.28
|
6.59
|
5.93
|
5.38
|
4.85
|
4.32
|
-
|
3.32
|
3.20
|
|
|
2. Gravel
|
8.21
|
7.56
|
6.87
|
6.21
|
5.63
|
5.10
|
4.60
|
-
|
3.57
|
3.20
|
|
|
3. Dirt
|
8.49
|
7.81
|
7.12
|
6.43
|
5.85
|
5.35
|
4.82
|
-
|
4.18
|
3.20
|
|
C
|
Alignment
fair:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Paved
|
7.93
|
7.28
|
6.75
|
6.25
|
5.75
|
5.22
|
4.68
|
-
|
3.89
|
3.89
|
|
|
2. Gravel
|
8.21
|
7.56
|
7.03
|
6.53
|
6.00
|
5.47
|
4.97
|
-
|
3.94
|
3.89
|
|
|
3. Dirt
|
8.49
|
7.81
|
7.28
|
6.75
|
6.21
|
5.72
|
5.18
|
-
|
4.15
|
3.89
|
|
D
|
Alignment
poor:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Gravel
|
8.45
|
7.95
|
7.42
|
6.92
|
6.39
|
5.86
|
5.36
|
-
|
4.68
|
4.68
|
|
|
2. Dirt
|
8.73
|
8.20
|
7.67
|
7.14
|
6.61
|
6.11
|
5.58
|
-
|
4.68
|
4.68
|
3
|
Single lane
with turnouts (truck lane without ditch)[2]:
|
|
|
|
|
|
|
|
|
|
|
|
B
|
Alignment good:
|
|
|
|
|
|
|
|
|
|
|
|
|
3. Dirt
|
8.49
|
7.81
|
7.12
|
6.45
|
5.92
|
5.42
|
4.88
|
-
|
3.85
|
3.28
|
|
C
|
Alignment
fair:
|
|
|
|
|
|
|
|
|
|
|
|
|
3. Dirt
|
8.49
|
7.93
|
7.40
|
6.86
|
6.33
|
5.83
|
5.30
|
-
|
4.27
|
4.08
|
|
D
|
Alignment
poor:
|
|
|
|
|
|
|
|
|
|
|
|
|
3. Dirt
|
9.03
|
8.49
|
7.96
|
7.43
|
6.90
|
6.40
|
5.87
|
-
|
5.28
|
5.28
|
[1] Alignment classification basis:
Poor
|
=
|
Average
radius (meter)
No . of curves per km
|
=
|
less
than 4
|
Fair
|
=
|
do.
|
=
|
4
to 10
|
Good
|
=
|
do.
|
=
|
10
to 20
|
Excellent
|
=
|
do.
|
=
|
over
20
|
[2] On single-lane or lane-and-one-half roads,
increase the time for passing vehicles on turnout by the percent shown in
following tabulation. Consider all vehicles for single-lane roads and only
trucks for lane-and-one-half roads.
Turnout
spacing (meter)
|
Increased
time when number of vehicles passing over road per hour is ....
|
5
|
10
|
15
|
20
|
|
Percent
|
Percent
|
Percent
|
Percent
|
75
|
2.0
|
4.0
|
6.0
|
8.0
|
150
|
2.6
|
5.4
|
8.0
|
10.7
|
225
|
3.4
|
6.8
|
10.2
|
13.6
|
|
Table 10b. Relationship between round trip travel time per
kilometer and surface type as influenced by vertical and horizontal
alignment; favorable grade in direction of haul (U.S. Forest service, 1965).
Class
of Road [1]
|
Percent
Grade in Direction of Load (Favorable)
|
0
|
-2
|
-4
|
-6
|
-7
|
-8
|
-9
|
-11
|
-12
|
-14
|
min
/ km
|
1
|
Lane and
one-half with turnouts (car lane and truck lane with 4-ft. ditch)[2]
|
|
|
|
|
|
|
|
|
|
|
|
A
|
Alignment
excellent:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Paved
|
2.42
|
2.42
|
2.47
|
2.89
|
3.22
|
3.53
|
3.87
|
4.53
|
4.87
|
5.59
|
|
|
2. Gravel
|
2.42
|
2.42
|
2.53
|
2.97
|
3.31
|
3.65
|
3.97
|
4.62
|
4.97
|
5.68
|
|
B
|
Alignment
good:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Paved
|
3.01
|
3.01
|
3.01
|
3.05
|
3.22
|
3.53
|
3.87
|
4.53
|
4.87
|
5.59
|
|
|
2. Gravel
|
3.01
|
3.01
|
3.01
|
3.13
|
3.32
|
3.65
|
3.97
|
4.62
|
4.97
|
5.68
|
|
C
|
Alignment
fair:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Paved
|
3.61
|
3.61
|
3.61
|
3.61
|
3.61
|
3.67
|
3.87
|
4.53
|
4.87
|
5.59
|
|
|
2. Gravel
|
3.61
|
3.61
|
3.61
|
3.61
|
3.61
|
3.80
|
3.97
|
4.62
|
4.97
|
5.68
|
2
|
Single lane
with turnouts (truck lane with 3-ft. ditch)[2]
|
|
|
|
|
|
|
|
|
|
|
|
A
|
Alignment
excellent:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Paved
|
2.58
|
2.58
|
2.58
|
2.89
|
3.22
|
3.53
|
3.87
|
4.53
|
4.87
|
5.59
|
|
|
2. Gravel
|
2.58
|
2.58
|
2.62
|
2.97
|
3.31
|
3.65
|
3.97
|
4.62
|
4.97
|
5.68
|
|
B
|
Alignment
good:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Paved
|
3.20
|
3.20
|
3.20
|
3.20
|
3.34
|
3.53
|
3.87
|
4.53
|
4.87
|
5.59
|
|
|
2. Gravel
|
3.20
|
3.20
|
3.20
|
3.25
|
3.44
|
3.65
|
3.97
|
4.62
|
4.97
|
5.68
|
|
|
3. Dirt
|
3.20
|
3.20
|
3.20
|
3.31
|
3.50
|
3.72
|
4.06
|
4.72
|
5.06
|
5.75
|
|
C
|
Alignment
fair:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Paved
|
3.89
|
3.89
|
3.89
|
3.89
|
3.89
|
3.89
|
4.02
|
4.53
|
4.87
|
5.59
|
|
|
2. Gravel
|
3.89
|
3.89
|
3.89
|
3.89
|
3.89
|
3.95
|
4.11
|
4.62
|
4.97
|
5.68
|
|
|
3. Dirt
|
3.89
|
3.89
|
3.89
|
3.89
|
3.89
|
4.02
|
4.20
|
4.72
|
5.06
|
5.75
|
|
D
|
Alignment
poor:
|
|
|
|
|
|
|
|
|
|
|
|
|
1. Gravel
|
|
|
|
|
|
|
|
|
|
|
|
|
2. Dirt
|
4.68
|
4.68
|
4.68
|
4.68
|
4.68
|
4.68
|
4.68
|
4.88
|
5.07
|
5.68
|
3
|
Single lane
with turnouts (truck lane without ditch)[2]:
|
4.68
|
4.68
|
4.68
|
4.68
|
4.68
|
4.68
|
4.68
|
4.98
|
5.17
|
5.75
|
|
B
|
Alignment good:
|
|
|
|
|
|
|
|
|
|
|
|
|
3. Dirt
|
3.28
|
3.28
|
3.28
|
3.33
|
3.52
|
3.72
|
4.06
|
4.72
|
5.06
|
5.75
|
|
C
|
Alignment
fair:
|
|
|
|
|
|
|
|
|
|
|
|
|
3. Dirt
|
4.08
|
4.08
|
4.08
|
4.08
|
4.08
|
4.09
|
4.28
|
4.72
|
5.06
|
5.75
|
|
D
|
Alignment
poor:
|
|
|
|
|
|
|
|
|
|
|
|
|
3. Dirt
|
5.28
|
5.28
|
5.28
|
5.28
|
5.28
|
5.28
|
5.28
|
5.28
|
5.47
|
5.82
|
[1] Alignment classification basis:
Poor
|
=
|
Average
radius (meter)
No . of curves per km
|
=
|
less
than 4
|
Fair
|
=
|
do.
|
=
|
4
to 10
|
Good
|
=
|
do.
|
=
|
10
to 20
|
Excellent
|
=
|
do.
|
=
|
over
20
|
[2] On single-lane or lane-and-one-half roads,
increase the time for passing vehicles on turnout by the percent shown in
following tabulation. Consider all vehicles for single-lane roads and only
trucks for lane-and-one-half roads.
Turnout
spacing (meter)
|
Increased
time when number of vehicles passing over road per hour is ...
|
5
|
10
|
15
|
20
|
|
Percent
|
Percent
|
Percent
|
Percent
|
75
|
2.0
|
4.0
|
6.0
|
8.0
|
150
|
2.6
|
5.4
|
8.0
|
10.7
|
225
|
3.4
|
6.8
|
10.2
|
13.6
|
|
Economic Evaluation and Justification
Economic Analysis Methods
A long range
plan, including road planning, is the basis for an economically, as well as
environmentally, sound road system. A well planned road system will result in
the least amount of roads to economically serve an area or watershed. It will
also result in the least amount of sediment delivery to streams as shown in
Figure 1.
The first step
in road access planning is to determine the optimum road spacing for a given
commercial use. A break-even analysis can often be applied. Plotted
graphicallly, the optimum spacing would lie at the minimum total cost, or the
intersection of the cost lines. Additional information can be found in Pearce
(1960), Dietz et al (1984), Von Segebaden (1964), and others.
An economic
evaluation of a particular road standard will require a rough estimate of
road construction costs be determined from road design data and from locally
available cost information for the various cost components. Likewise, annual
maintenance cost per kilometer of road is best estimated based on local
experience for comparable roads. Trucking cost data will consist of the
average cost per round-trip kilometer of haul over the road and would take
into consideration travel time (see Section 2.1), fixed costs (depreciation,
interest, insurance, etc.), operating costs per minute driving time (fuel,
lubrication, repairs), dependent costs per minute driving time plus delay
time (driver's wage, social security tax, unemployment compensation,
administration), and tire cost per mile by surface type.
The combined
annual costs of road construction, maintenance, and trucking make up the
annual cost:
A =
R + I + M + T
where A is total
annual cost per kilometer, R is annual cost per kilometer of road
construction for the amortization period, I is average annual interest cost,
M is annual maintenance cost per kilometer, and T is average trucking cost
per kilometer for the annual commodity volume to be hauled over the road.
EXAMPLE:
Assume the
following costs (in US dollars) have been estimated for three classes of
road. (Annual volume of commodity, 10 million cubic meters.)
ROAD
CLASS
|
I
|
II
|
III
|
Construction
cost per kilometer
|
$40,000.00
|
$22,000.00
|
$15,000.00
|
Maintenance
cost per kilometer
|
300.00
|
400.00
|
500.00
|
Trucking cost
per 1,000 m³ per kilometer
|
0.25
|
0.30
|
0.35
|
Trucking cost
per annum per kilometer
|
2,500.00
|
3,000.00
|
3,500.00
|
Annual cost
per km over 25 years
|
|
|
|
R road
construction cost
|
1,600.00
|
880.00
|
600.00
|
I interest
costs
|
700.00
|
383.00
|
262.00
|
M maintenance
cost
|
300.00
|
400.00
|
500.00
|
T trucking
cost
|
2,500.00
|
3,000.00
|
3,500.00
|
A Total Annual
Costs
|
$5,100.00
|
$4,663.00
|
$4,862.00
|
(If amortization
period is 25 years, the annual rate is 4 percent of the construction cost. If
the interest rate is 3.5 percent, the average annual interest rate is 1.75
percent.)
Note that in the
above calculation the Class II road is the most economical by a margin of
$199.00 over the Class III road. Over the period of amortization of 25 years,
the margin for the Class II road will be $4,975.00 per kilometer.
Another method
in choosing the most economical of two road standards is to calculate the
annual amount or volume of commodity at which the costs of the two roads will
be equal. If annual volume exceeds the calculated amount the higher road
standard will be justified; likewise, if annual volume is less than the
calculated amount, the lower standard is justified. The formula for
calculating V is:
V
=
|
(R
+ I + M)H - (R + I + M)L
|
TL
- TH
|
The subscripts H
and L indicate high and low standard, respectively, and T is expressed as
cost per 1000 m³ per kilometer. Ail other values are expressed in units
stated above.
EXAMPLE:
Using the same
costs as in the previous example for the Class II and Class III road, the
annual volume is calculated as:
V
=
|
(880
+ 383 + 400) - (600+ 262 + 500)
|
= 6,020 x
10(3) m³
|
(0.35
- 0.30)
|
Hence, for
volumes exceeding 6.02 x 106, m³ the Class II road is the more economical
choice; for volumes less than 6.02 x 106 m³ the Class III road would be
chosen. If the two roads differ in length, multiply the costs per kilometer
by the number of kilometers of each road for use in this formula.
Analysis of Alternative Routes
The above
formulas can also be used to evaluate two or more alternatives to a proposed
route. One common situation is to choose between a longer route on a gentle
favorable grade and a shorter route involving an adverse grade and a steeper
favorable grade.
EXAMPLE:
1. Longer
route segment: 3.67 km of 3% favorable grade. Trucking cost = $.562 per
1000 m³; construction cost $55,050 at 6% amortization plus interest = $3,303;
annual maintenance at $300/km = $1,101. Total annual cost = $4,404.
2. Shorter route segment: 2.0 km of 8% favorable grade, 1 km of 5%
adverse grade. Trucking cost = $.81 per 1000 m³; construction cost $41,000 at
6% amortization plus interest = $2,460; annual maintenance at $400/km
(steeper grade, sharper curves) = $1,200. Total annual cost = $3,660.
V =
(4,404 - 3,660)/(0.81 - 0.562) = 3 x 10(6) m³
(According to
the formula, the longer route will be the more economical if the annual
volume hauled exceeds 3 million cubic meters.)
In justifying
the added capital investment to achieve greater road stability the risk of
potential cost of a road failure must also be weighed in the balance. This
type of risk analysis is commonly done when determining culvert size for a
particular stream crossing. The probability of occurrence of a peak flow
event which would exceed the design capacity of the proposed culvert
installation must be determined and incorporated into the design procedure.
The 1964-65 winter season floods occurring throughout the Pacific Northwest
Region of the United States have been classified as 50; to 100-year return
interval events. ("Return interval" is defined as the length of
time that a storm event of specified magnitude would be expected to reoccur.
A 50-year event, therefore, would be expected to occur, on the average, once
every 50 years.) Damages to transportation structures (roads, bridges,
trails) in Oregon was estimated at $12.5 million, or, 4 percent of the total
investment of $355 million not including destruction of stream habitat, water
quality, private property, and "down time" and other inconveniences
associated with these losses.
As mentioned
earlier in this handbook, constructing roads specifically to control erosion
may not cost any more than constructing roads using conventional methods. The
money invested to achieve satisfactory levels of stability while still
meeting design criteria will generally be recouped over the life of the road
in reduced maintenance costs, serviceability, longer life, and reduced
impacts on stream habitat and water quality. The goal of fitting roads to the
terrain and adopting appropriate road standards to achieve that goal will
often result in reduced earthwork per station.
Incremental
costs for roads built to high standards of construction (compacted fills,
surface treatments, terraced fills, etc.) associated with the amount of
reduction of sediment yield is difficult to generate since such wide
variability exists in equipment and labor costs, environmental factors (such
as soil erodibility), and operator skill. Gardner (1971) has developed some
rudimentary data for comparing annual road costs for single and double lane
roads with differing surface treatments depreciated over 20 years and using 6
percent capital recovery. The author suggests that user cost for
environmental protection is represented as the difference in annual cost
between two-lane paved and one-lane gravel roads in Table 11. More detailed
comparisons of annual cost per km at different user levels is presented in Tables
12 and 13.
Table 11. Comparison of single-lane versus double-lane
costs at three different use levels.
Number
of Vehicles per year
|
Total
annual cost per kilometer
|
1 lane gravel
|
2 lane paved
|
Difference
|
US
Dollars
|
10,000
|
3,440
|
4,200
|
-760
|
20,000
|
5,800
|
5,690
|
+112
|
40,000
|
10,530
|
8,680
|
+1,790
|
Table 12. Comparison of annual road costs per kilometer
--10,000 vehicles per year.
Cost
distribution
|
Road
Standard
|
2 lane
paved
|
2 lane
chip-seal
|
2 lane
gravel
|
1 lane
gravel
|
1 lane spot stabilization
|
1 lane
primitive
|
Dollars
per Kilometer
|
Initial
Construction
|
$31,070
|
$24,860
|
$18,640
|
$12,430
|
$9,320
|
$6,210
|
|
Dollars
per kilometer per year (20-year period)
|
Depreciation[1]
|
2,710
|
2,170
|
1,620
|
1,080
|
810
|
540
|
Maintenance
|
120
|
250
|
370
|
500
|
680
|
310
|
Vehicle use
|
1,370
|
1,430
|
1,680
|
1,860
|
2,730
|
5,280
|
Total annual
|
4,200
|
3,850
|
3,670
|
3,440[2]
|
4,230
|
6,130
|
[1] 20 years
at 6% using capital recovery.
|
[2] Lowest
annual cost.
|
Table 13. Comparison of annual road costs per kilometer
for 20,000 and 40,000 vehicles per year
Cost distribution
|
Road
Standard
|
2 lane
paved
|
2 lane chip-seal
|
2 lane
gravel
|
1 lane
gravel
|
1 lane spot stabilization
|
1 lane
primitive
|
Dollars
per Kilometer
|
construction
|
31,070
|
24,860
|
18,640
|
12,430
|
9,320
|
6,210
|
|
Dollars
per kilometer per year (20-year period)
20,000 vehicles per year
|
Depreciation[1]
|
2,710
|
2,170
|
1,620
|
1,080
|
810
|
540
|
Maintenance
|
250
|
500
|
750
|
1,000
|
1,370
|
620
|
Vehicle use
|
2,730
|
2,860
|
3,360
|
3,730
|
5,470
|
10,560
|
Total annual
|
5,690
|
5,5302
|
5,730
|
5,810
|
7,650
|
11,720
|
|
Dollars
per kilometer per year (20-year period)
40,000 vehicles per year
|
Depreciation
|
2,710
|
2,170
|
1,620
|
1,080
|
810
|
540
|
Maintenance
|
500
|
1,000
|
1,490
|
1,990
|
2,730
|
1,240
|
Vehicle
use
|
5,470
|
5,720
|
6,710
|
7,460
|
10,940
|
21,130
|
Total
annual
|
8,680[2]
|
8,890
|
9,820
|
10,530
|
14,480
|
22,910
|
[1] 20 years
at 6% using capital recovery.
|
[2] Lowest
annual cost.
|
Gardner (1978)
analyzed alternative design standards and costs in addition .
|